Back to Cases

Powering an installation schedule by going the distance.

Related downloads

The case

Samsung Heavy Industries has entered the European offshore wind market in a big way. Their prototype seven megawatt wind turbine in the Energy Park Fife, Scotland, is the largest in the world – capable of powering 4,800 homes. But transporting and installing the SHI turbine demanded creative engineering. The approved location was located in shallow water just 47 meters off the coast of Scotland, and this prevented a traditional approach using heavy lift vessels. Mammoet offered a comprehensive approach that proved to be the fastest and safest.

REACHING FURTHER WITH CLEVER THINKING AND UNIQUE EQUIPMENT. 

The answer to the shallow water challenge at Energy Park Fife was to install from the land, and that required a smart lifting solution. The 18 meters long nacelle had to be installed at a height of 116 meters, and at a point more than 50 meters from where the crane was positioned. The customer favored Mammoet’s approach using a single crane for installation – other contractors had proposed the use of two. The Mammoet plan was faster because it required less preparation time. It was also considered safer given the distance to the foundation, because it eliminated the need for complex coordination of two cranes.

Smart lifting solution installs offshore wind turbines swifter and safer from land.

Samsung Heavy Industries Fife, Scotland

But first, all components needed to be moved to the destination site. Mammoet arranged the transport of the 83.5 meter long blades from the Danish factory in Kirkeby. To ensure safe transport of the blades, Mammoet had designed special transport frames for the truck and dollies. Meanwhile, the tower and nacelle had arrived in the Port of Rotterdam, coming from their fabrication yards in China and South-Korea. From there, Mammoet shipped them onto low-draft coasters, right on schedule.

May 2013 Transshipment of tower parts in Rotterdam

July 2013 Special transport of 83.5 meter blade

Sep 2013 Installation has begun

Sep 2013 Nearing completion

Once all components arrived on-site, Mammoet installed the piles, jacket and transition piece. Then, the tower was erected and installed on the steel jacket foundation by one of Mammoet’s bigger crawler cranes assisted by a 600 ton tailing crane. The installation of the nacelle and three rotor blades completed the construction work. Today the seven megawatt SHI turbine is performing its test program, standing tall at 196 meters. 

Share this page

Get in touch

Do you have a question about a project or you have similar project. Get in touch with the right person and use our contact form. 

Contact us

You might also like