Carlos Moreno, lead segment Onshore Wind at Mammoet
Sector:
  • Onshore Wind

Expertise:
  • Heavy lifting

  • Heavy transport

Mammoet Onshore Wind Segment Lead, Carlos Moreno, explains how to hit a moving target.

The pace of change in onshore wind is quite staggering. This is true both figuratively - as countries move towards more sustainable energy sources - and physically, as developers reach to higher elevations where winds are stronger and more reliable.

It is a truly exciting time – in what other industry can you see an increased yield of 100% in half a decade? Or a size increase of nearly 300% - from 60m hub height to approaching 175m - in a similar timeframe?

As turbine heights and diameters grow, so does the power per turbine - with the generation of over 5.5MW now possible. When the pace of the industry is this fast, constant innovation is needed to meet its many challenges.

One such challenge is that specialized lifting technologies available in the marketplace are currently limited to around 160m hub height. Truck-mounted cranes with strengthened lattice booms have been widely used but going beyond this height becomes a challenge.

Onshore wind turbine during installation

Building over 160m requires heavy crawler cranes that are not designed for wind farm installations; their significant assemblyrelocation times and wind speed resistance are ill-suited to such a fast-paced seasonal industry. They also have relatively low market availability and global spread.

These heavier lifting machines bring further challenges. Extra civil works can be required to accommodate crawler cranes’ larger working radius, along with wider areas to move counterweights, long boom down corridors and relatively lengthy processes to relocate the crane between wind turbine pads.

This is why tower cranes like the Kroll K1650L have been used for high-hub height installations. They are especially useful on projects where the topography of the site is an issue; when aspects like removing trees or preparing pads on mountainous sites become too costly.

wind turbine assembly

So, it is increasingly important that installation costs are considered from a broader point of view, allowing savings to be made from the design of the turbines themselves, through the preparation of the site, to the lifting process itself. This requires close coordination between OEM, developer, and heavy lift engineer, to ensure the whole process is optimized.

Mammoet is committed to bringing cleaner, cheaper energy to the world, and so we are always on the lookout for ways to solve our customers’ challenges. In this case, how to reduce ground works while at the same time offering installation heights above 160m.

Solving this challenge will lower installation costs, increase returns for developers, stimulate further growth in wind energy, and lower the cost of electricity for consumers.