Sector:
  • Civil Engineering

Expertise:
  • Heavy transport

Benefits:
  • Reduced preparation

  • Reduced disruption

  • Protected infrastructure

  • Simplified management

Location:
  • United Arab Emirates

Building a metro line at the speed of Dubai.

In two decades, Dubai has exploded into the bustling desert metropolis it is today. Catering to its rapid expansion, the city was in need of a new metro line.

The 47.4-kilometer line had to be completed within a two-year timeframe. Mammoet was contracted to plan, coordinate and execute the delivery of 13,067 concrete elements that had to be placed in a specific order and on a strict schedule.

Facing difficult delivery locations ranging from busy highways to areas without road access, Mammoet solved the complex puzzle and successfully delivered all pieces within the 24-month timeframe.

The biggest challenge was maintaining a constant stream of up to 40 concrete elements per day - in the right order - for two years. Any disruptions in the supply or changes in the order would impact the overall production schedule of the metro line.

To make matters more difficult, the deliveries had to take place at night in order to minimize interference with Dubai’s busy everyday life. But being one of the most congested cities in the world, even nighttime operations could be seriously hindered by local traffic and vice versa.metro modular part for the construction.jpg

Before transporting any element, Mammoet engineers surveyed the entire route to every location. Not only to assess that safe delivery was in fact possible but also to check if any precautions were needed, such as reinforcing existing roads or building temporary new ones to accommodate the heavy loads.

The metro line’s concrete pier caps and viaduct segments couldn’t be safely transported with existing equipment at all. Therefore, Mammoet’s engineers created specially designed saddles for transportation.

At the peak of the operation, an average of 20 trailers made two trips each night for an entire month, during which Mammoet delivered 877 viaduct segments and 84 pier caps along the metro line. When the metro went underground, Mammoet delivered a tunnel boring machine 25 meters below the surface. For two years, Mammoet worked non-stop to ensure timely delivery of all elements and, as a result, contribute to a solid connection between the far corners of the vast city of Dubai.