Sector:
Mining & Metals
Expertise:
Project logistics
Skidding
Jacking
Benefits:
Reduced preparation
Optimized schedule
Location:
South Africa
Vanadium is a metal element that is used as an additive for steel, increasing its strength for use in tools, surgical instruments, and even jet engines.
During production, its ore is placed into a large tank containing a special solution, which leaches the vanadium from it, which falls to the base for collection.
Mammoet was chosen to transport four such tanks from their point of manufacture near Johannesburg to a mine site in North West province. It advised on delivery strategy from an early stage, allowing the client to avoid an onsite stick-build approach that would have posed many challenges, such as requiring workers to be fitted with gas masks and causing the potential to produce a non-watertight vessel.
Instead, the tanks were delivered as a complete module from their location of manufacture in Vanderbijlpark, a distance of 252.3km from the site. One after the other over a course of seven months, the tanks were received, transported across one of the country’s most metropolitan provinces, and installed.
The tanks were received at the workshop, where they were jacked up to a height of approximately two meters by four 150t jacks. Following this, a prime mover fitted with a Cometto 18-axle 2 file trailer was reversed underneath the tank, ultimately taking the load.
The transportation route had been planned optimally around the nearby cities of Johannesburg and Pretoria. Nevertheless, Mammoet had obtained a wealth of transport permits, de-energizing and lifting services for overhead power cables along the route, and escorts from local law enforcement, where required.
Upon reaching the mine site, a significant challenge was still presented by its compactness, and the many buildings in place nearby. To combat this, the tanks were staged onto stools and reloaded onto two SPMTs in a 2 x 6-axle configuration.
During installation, the tanks were jacked-up using the same equipment as before, then lowered onto a jacking and skidding system consisting of four skidding tracks, eight skidding beams, and four push-pull cylinders. The base of the tank is designed to lie at an angle, allowing vanadium deposits to be scraped up and harvested, and so Mammoet designed a swivel and interfacing point that maneuvered to the required 2° tilt.
At 41.4m x 7.57m x 6.91m and at 263t, the leach tanks were some of the largest items ever to be transported through Gauteng province. Each transportation and installation procedure combined took approximately two weeks to complete.
The mine is expected to output over 3,400 mega tonnes of vanadium during 2020, rising to 5,000 in the near future as part of this expansion program – providing southern Africa with a vital building block of industry and technology.