Sector:
  • Civil Engineering

Expertise:
  • Heavy transport

  • Skidding

Benefits:
  • Reduced disruption

  • Protected infrastructure

  • Parallel operations

Location:
  • Netherlands

Months of planning changed Rotterdam’s skyline overnight. In 2003, Unilever’s new headquarters changed the Rotterdam skyline.

But before it did, it had to be placed on top of the existing factory, without impacting the operations below. Together with Mammoet, Unilever decided to build a new office next to the factory.

Once the building – nicknamed The Bridge – was finished, it was positioned in its final position above the existing facilities in one go. The job was completed in a single weekend, in time for the Monday morning shift to get to work.

Constructing a 3,500-ton building on top of a factory was going to take months. Considering the prolonged impact this would have on Unilever's day-to-day operations, this scenario wasn't an option. The factory would have to be shut down for a large part of the construction process, supply routes would be heavily obstructed and costs would soar as a direct result.

With the reduction of downtime in mind, we suggested a radically different approach. Together with the client and our production partners, the decision was made to build the new office next to the factory and then place one on top of the other in one go. Not only would this solution save Unilever a significant amount of time and money, but it also meant that the construction could take place in a controlled environment, greatly enhancing the safety of both construction workers and factory personnel.

Last but not least, Mammoet's approach was the most efficient solution to get the building in place without interrupting Unilever's operations. Through a tailor-made combination of SPMTs and a skidding system, the entire structure was safely moved into position over the weekend.

By carrying out the bulk of the construction process off-site, the job on location took a relatively short time to complete. Having started the operation on Saturday, the factory was back open for business the very next Monday morning. As if The Bridge had always been there.

Skidding The Bridge over the factory
Final location